PMI-RMP - Ethics in Risk Management - Accountability and Responsibility in Risk Management
Expert
1/5
When implementing a risk response strategy, what is the most appropriate way to ensure clear accountability?
a.
Create a matrix of shared responsibilities between project stakeholders for risk mitigation
b.
Assign a single responsible person for each risk response action
c.
Establish a rotating schedule of risk response ownership among qualified team members
d.
Distribute risk response responsibilities among multiple team members based on their expertise