PMI-RMP - Implementing Risk Responses - Managing Secondary and Residual Risks
Intermediate
1/5
After implementing primary risk responses, a project experiences reduced exposure to certain risks but not complete elimination. Which of the following statements describes the correct approach to managing these remaining risk levels?
a.
Consider remaining risk levels as acceptable since primary responses have already been implemented according to plan
b.
Assess the remaining risk levels and apply additional responses if they exceed the risk tolerance threshold
c.
Transfer the responsibility of managing remaining risk levels to the operational team once primary responses are in place
d.
Document all remaining risk levels in detail and proceed with project activities as the primary responses have been completed