PMI-RMP - Implementing Risk Responses - Risk Ownership and Assignment
Beginner
1/5
Which statement best describes the optimal timing for assigning risk ownership in a project?
a.
During the project closure phase when all risk impacts have been fully assessed and documented
b.
After comprehensive risk analysis and response planning has been completed by the team
c.
At the point of risk identification, when the risk's characteristics are clear
d.
When the project steering committee approves the risk management strategy and plan