PMI-RMP - Introduction to Risk Management - Risk Response Planning
Intermediate
1/100
Which stakeholder typically has the primary responsibility for authorizing additional risk response resources when risk impacts exceed initial contingency budgets?
a.
Project Sponsor
b.
Risk Management Team Leader and Financial Controller
c.
The Project Risk Committee which oversees all major risk-related expenditures
d.
Program Management Office Director and Risk Board