PMI-RMP - Perform Specialized Risk Analyses - Bow-Tie Analysis in Risk Management
Intermediate
1/5
A Risk Breakdown Structure (RBS) for a project shows numerous risks with duplicate subcategories spread across all levels of the hierarchy. What key principle of RBS design is being violated?
a.
Each risk category should maintain complete alignment with the project's WBS structure
b.
The hierarchy must contain both quantitative and qualitative risk metrics at each level
c.
Each risk category should be mutually exclusive
d.
Risk categories must be arranged by their probability of occurrence in descending order
Intermediate