Program Evaluation and Review Technique (PERT)

5 minutes 5 Questions

Program Evaluation and Review Technique (PERT) is a statistical tool used in project management that incorporates uncertainty by utilizing three different time estimates—optimistic, most likely, and pessimistic—to calculate an expected duration for activities and the overall project. This technique…

Test mode:
PMI-RMP - Program Evaluation and Review Technique (PERT) Example Questions

Test your knowledge of Program Evaluation and Review Technique (PERT)

Question 1

Question: Angela is managing a construction project. To calculate the expected time for tasks, she only considers the most optimistic time. Is this a correct approach to PERT Analysis?

Question 2

Nick is analyzing the variance for each activity in his project management process. For task V, optimistic time is 5 days, most likely time is 7 days, and pessimistic time is 14 days. What will be the variance for this task in PERT Analysis?

Question 3

In PERT Analysis, what is the significance of the difference between the pessimistic and optimistic time estimates?

More Program Evaluation and Review Technique (PERT) questions
21 questions (total)