Availability Heuristic in Risk Assessment

5 minutes 5 Questions

The Availability Heuristic in Risk Assessment is a cognitive bias where individuals estimate the likelihood of an event based on how easily examples come to mind. In the context of risk management, this can lead to overestimating the probability of risks that are more memorable or recent, while und…

Test mode:
PMI-RMP - Availability Heuristic in Risk Assessment Example Questions

Test your knowledge of Availability Heuristic in Risk Assessment

Question 1

In a construction project risk assessment, stakeholders are placing excessive importance on risks they can easily recall from vivid news reports about similar projects. Which cognitive bias best describes this behavior?

Question 2

During a project's risk assessment workshop, participants tend to assign higher probabilities to risks that have attracted recent media attention. When analyzing this behavioral pattern from a psychological perspective, what does this represent?

Question 3

In a PMO meeting, a risk analyst suggests implementing a new decision-making framework to address the availability heuristic. What would be the primary benefit of this approach?

More Availability Heuristic in Risk Assessment questions