PMI-RMP - Risk Management Tools and Techniques - Influence Diagram
Intermediate
1/5
According to PMI's Risk Management guidelines, who is primarily responsible for ensuring risk thresholds are properly defined and monitored throughout the project?
a.
The Risk Manager in collaboration with key stakeholders
b.
The Project Manager and the Risk Management team in consultation with external consultants
c.
The Program Manager with approval from the Project Steering Committee
d.
The Risk Management Committee and senior leadership team members