Workarounds

5 minutes 5 Questions

Workarounds are unplanned responses developed to address unforeseen risks that arise during the course of a project. They are implemented when identified risks occur and the planned risk responses are not effective or when new risks emerge that were not previously identified or planned for. Workarounds are essential in risk monitoring and control because they provide a means to handle issues in real-time, ensuring that the project can continue progressing towards its objectives despite unexpected obstacles. In the context of risk monitoring and control, project managers must remain vigilant for new risks and be prepared to develop workarounds swiftly. This involves quick decision-making and problem-solving skills to mitigate the impact of the unexpected risk on the project's scope, schedule, cost, and quality. Workarounds are typically documented and included in the project’s risk register once they are identified and implemented. This documentation is crucial for tracking and for future reference, as it contributes to organizational learning and can be used to inform risk management practices in future projects. Implementing workarounds may also require adjustments to project plans, resource allocations, and may have implications for stakeholders. Effective communication is therefore key when implementing workarounds, ensuring that all affected parties are informed of changes and understand the reasons behind them. Additionally, workarounds should be monitored for effectiveness after implementation, and further adjustments should be made as necessary. This iterative process helps to minimize the negative impacts of risks and supports the overall risk management strategy within the project.

Comprehensive Guide to Workarounds in Risk Monitoring and Control

What are Workarounds in Project Risk Management?

Workarounds are unplanned responses developed to deal with realized risks that were previously unidentified or accepted passively. Unlike planned risk responses, workarounds are reactive measures implemented when a risk actually occurs and no contingency plan exists.

Why Workarounds Are Important

Workarounds play a crucial role in project risk management for several reasons:

1. Reality of Project Management: No matter how thorough risk identification is, not all risks can be anticipated.

2. Business Continuity: They allow projects to continue despite unexpected problems.

3. Adaptability: They demonstrate a project team's ability to adapt and respond to unforeseen circumstances.

4. Learning Opportunity: Each workaround provides valuable lessons for future projects and risk planning.

How Workarounds Work in Practice

The process typically follows these steps:

1. Risk Occurrence: An unidentified or passively accepted risk materializes.

2. Impact Assessment: The project team quickly assesses the impact on project objectives.

3. Solution Development: The team develops an impromptu solution to address the issue.

4. Implementation: The workaround is implemented to mitigate the impact.

5. Documentation: The workaround and its effectiveness are documented for future reference.

6. Incorporation into Risk Register: The risk and its workaround may be added to the risk register for ongoing monitoring.

Examples of Workarounds

• A key team member leaves unexpectedly, and tasks are redistributed among remaining team members.

• A critical component is delayed in shipping, so the team sources an alternative supplier or uses a temporary substitute.

• Software compatibility issues arise during implementation, so the team creates a manual process until a technical solution is found.

Workarounds vs. Planned Responses

Planned Responses:
• Proactive
• Developed before risk occurs
• Part of the risk management plan
• Resource allocation is predetermined

Workarounds:
• Reactive
• Developed after risk occurs
• Not part of the original plan
• Resources must be allocated on the spot

Exam Tips: Answering Questions on Workarounds

1. Recognize the Context: Identify when a question is describing a workaround scenario (unplanned response to an unexpected risk).

2. Remember the Reactive Nature: Workarounds are always reactive, never proactive. If the question asks about proactive measures, a workaround is not the correct answer.

3. Distinguish from Contingency Plans: Don't confuse workarounds with contingency plans, which are prepared in advance for identified risks.

4. Focus on Documentation: Proper documentation of workarounds is essential - they should be recorded and potentially added to the risk register.

5. Link to Control Processes: Understand that workarounds are part of the Monitor and Control Risk process, not Plan Risk Responses.

6. Consider Resource Implications: Workarounds often require unplanned resource allocation, which may impact other project areas.

7. Look for Learning Opportunities: Good project management involves learning from workarounds to improve future risk identification.

8. Scenario Analysis: Practice analyzing scenarios where workarounds would be the appropriate response.

Key PMI-RMP Exam Considerations

• Workarounds represent a critical aspect of real-world risk management that the PMI-RMP exam often tests.

• They demonstrate your ability to think on your feet and adapt to changing circumstances.

• Questions may present scenarios and ask you to determine if a workaround is appropriate or what type of response is being described.

• Remember that while workarounds are necessary sometimes, they indicate a gap in risk identification that should be addressed in future projects.

• The PMI values both preparedness (risk planning) and adaptability (effective workarounds when needed).

By understanding the nature and appropriate use of workarounds, you'll be well-equipped to answer related questions on the PMI-RMP exam and apply this knowledge in real-world project risk management.

Test mode:
Go Premium

PMI Risk Management Professional Preparation Package (2025)

  • 3223 Superior-grade PMI Risk Management Professional practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PMI-RMP preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Workarounds questions
25 questions (total)