PMI-RMP - Risk Register and Documentation - Risk Triggers and Thresholds Documentation
Intermediate
1/5
When developing a Risk Breakdown Structure (RBS), what method ensures consistent hierarchical decomposition while maintaining flexibility for future risk adjustments?
a.
Implementing a color-coded matrix system that assigns specific shades to indicate the relationship between parent and child risk categories
b.
Establishing a dynamic tagging system where each risk category receives multiple identifiers based on its position in the hierarchy
c.
Using a decimal-based numbering system where each level adds a number (e.g., 1.0, 1.1, 1.1.1)
d.
Creating alphabetical codes combined with sequential numbers to represent each level of risk categorization and their interconnections
Intermediate