PMI-RMP - Stakeholder Engagement in Risk Management - Ethics and Transparency in Stakeholder Engagement in Risk Management
Expert
1/5
What is the most appropriate way to handle confidential risk-related information when communicating with stakeholders?
a.
Share all risk information equally with every stakeholder to maintain complete transparency in the project
b.
Release risk information only after getting approval from all project stakeholders
c.
Communicate risk information through informal channels to ensure rapid distribution to all parties
d.
Share information based on stakeholder classification and need-to-know basis
Expert