PMI-RMP - Stakeholder Engagement in Risk Management - Stakeholder Collaboration in Risk Response Strategies
Beginner
1/5
During risk response planning for a critical project initiative, what is the most effective approach for a Risk Manager to engage stakeholders in developing mitigation strategies?
a.
Facilitate collaborative workshops where stakeholders can jointly identify and evaluate response options
b.
Create a comprehensive risk response document and distribute it to stakeholders for their formal approval
c.
Schedule individual meetings with each stakeholder to collect their input on risk response strategies independently
d.
Send detailed email summaries of proposed risk responses and request stakeholders to provide feedback within 48 hours
Beginner