Leads and Lags
Leads and lags are scheduling techniques used to adjust the timing relationships between activities in a project schedule. They modify the logical relationships defined during activity sequencing to reflect real-world constraints and optimize the schedule. - **Lead:** A lead is an acceleration of …
PMI-SP - Leads and Lags Example Questions
Test your knowledge of Leads and Lags
Question 1
In a project where Activity A and Activity B have a lag of -5 days and a finish-to-start relationship, which statement best describes their relationship?
Question 2
In a construction project, Activity B was originally planned to start 3 days after Activity A finished. However, after schedule optimization, Activity B can now start when Activity A is 75% complete. What is this 3-day reduction in wait time between activities called?
Question 3
In a large software development project, when you need to model the overlap between testing and development phases using a finish-to-start relationship, what scheduling element represents a 10% completion of the predecessor before the successor can begin?