Precedence Diagramming Method (PDM)

5 minutes 5 Questions

The Precedence Diagramming Method (PDM) is a fundamental tool used in project scheduling for visually depicting the relationships between activities. In PDM, activities are represented as nodes (commonly rectangles), and dependencies between them are shown as arrows connecting these nodes. This method allows project managers to identify the sequence in which activities must be performed, establish the logical relationships, and determine the critical path of the project. There are four types of dependencies utilized in PDM to define the relationships between activities: 1. **Finish-to-Start (FS):** The successor activity cannot start until the predecessor activity finishes. This is the most common type of dependency. 2. **Finish-to-Finish (FF):** The successor activity cannot finish until the predecessor activity finishes. 3. **Start-to-Start (SS):** The successor activity cannot start until the predecessor activity starts. 4. **Start-to-Finish (SF):** The successor activity cannot finish until the predecessor activity starts. This type is rarely used. By employing PDM, project managers can effectively plan and control the project schedule. It facilitates the identification of potential scheduling issues early in the planning process, such as bottlenecks or resource conflicts. Additionally, PDM supports the application of critical path method (CPM) analysis to determine the minimum project duration and identify activities that have flexibility in their scheduling (float). Understanding and utilizing PDM is essential for efficient project scheduling and for communicating the project plan to stakeholders.

Test mode:
PMI-SP - Activity Definition and Sequencing Example Questions

Test your knowledge of Amazon Simple Storage Service (S3)

Question 1

In a Precedence Diagramming Method (PDM), if there are three activities A, B, and C where B has a Start-to-Start relationship with A and a Finish-to-Finish relationship with C, what best describes this activity network?

Question 2

In a Precedence Diagramming Method (PDM), when Task A has a positive lag of 2 days and a negative lag of 3 days with two different successor activities, what does this indicate?

Question 3

In the Precedence Diagramming Method (PDM), if Activity A and Activity B can start at the same time, but Activity B must finish 3 days after Activity A finishes, what relationship type and lag combination should be used?

Go Premium

PMI Scheduling Professional Preparation Package (2024)

  • 3429 Superior-grade PMI Scheduling Professional practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PMI-SP preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Precedence Diagramming Method (PDM) questions
53 questions (total)