PMI-SP - Activity Definition and Sequencing - Schedule Network Diagram
Beginner
1/5
In a Schedule Network Diagram, what does a Finish-to-Start (FS) relationship with a lag of +5 days between Activity A and Activity B indicate?
a.
Activity B should start 5 days after Activity A starts its execution phase
b.
Activity B must finish 5 days before Activity A starts
c.
Activity B can start 5 days after Activity A finishes
d.
Activity A and B must maintain a constant 5-day separation throughout their duration