Activity Sequencing and Dependencies in CPM

5 minutes 5 Questions

In Critical Path Method (CPM), activity sequencing and dependencies are fundamental concepts that determine the logical order in which project tasks are performed. Proper sequencing ensures that tasks are arranged in a logical flow, reflecting the real-world constraints and interrelationships between activities. Dependencies, also known as logical relationships, define how activities are connected and how one activity's timing affects another's. There are four primary types of dependencies: 1. **Finish-to-Start (FS)**: The most common type, where a successor activity cannot start until the predecessor has finished. 2. **Start-to-Start (SS)**: The successor activity cannot start until the predecessor activity starts. 3. **Finish-to-Finish (FF)**: The successor activity cannot finish until the predecessor activity finishes. 4. **Start-to-Finish (SF)**: The successor activity cannot finish until the predecessor activity starts. By accurately identifying these dependencies, project managers can develop a realistic project schedule that accounts for the necessary order of operations. Misidentifying dependencies can lead to scheduling conflicts, resource overallocations, and project delays. Activity sequencing involves mapping out these dependencies in a network diagram, which visually represents the project's activities and their relationships. This diagram serves as a critical tool for performing the forward and backward passes in CPM to calculate early and late start and finish dates, ultimately identifying the critical path. Understanding activity sequencing and dependencies allows project managers to: - **Optimize Project Schedules**: By identifying the most efficient sequence of activities, potential delays can be minimized. - **Identify Critical Activities**: Knowing which activities are critical helps in focusing resources and monitoring progress. - **Enhance Communication**: A clear activity sequence provides stakeholders with a transparent view of the project plan. - **Facilitate Risk Management**: Recognizing dependencies helps in identifying potential risks associated with schedule delays. In summary, activity sequencing and dependencies are essential for creating an accurate and effective project schedule using CPM. They ensure that all necessary task relationships are considered, which is crucial for the successful planning and execution of a project.

Activity Sequencing and Dependencies in CPM: A Comprehensive Guide

Understanding Activity Sequencing and Dependencies in Critical Path Method (CPM)

Activity sequencing and dependencies form the foundation of the Critical Path Method (CPM), a crucial project management technique for scheduling complex projects. This guide will help you understand why it's important, what it entails, how it works, and how to excel in exam questions on this topic.

Why Activity Sequencing and Dependencies are Important

Activity sequencing and establishing dependencies in CPM are vital because they:

- Provide logical structure to project activities
- Enable accurate schedule development
- Help identify the critical path
- Allow for realistic estimation of project duration
- Facilitate resource allocation and optimization
- Enable effective risk management
- Support schedule compression when necessary

What Are Activity Sequencing and Dependencies?

Activity sequencing is the process of identifying and documenting the logical relationships between project activities. Dependencies are the relationships between these activities that determine the order in which they must be performed.

Types of Dependencies in CPM:

1. Finish-to-Start (FS): The most common dependency. The successor activity cannot start until the predecessor activity finishes.

2. Start-to-Start (SS): The successor activity cannot start until the predecessor activity starts.

3. Finish-to-Finish (FF): The successor activity cannot finish until the predecessor activity finishes.

4. Start-to-Finish (SF): The successor activity cannot finish until the predecessor activity starts (rarely used).

Categories of Dependencies:

- Mandatory Dependencies (Hard Logic): Inherent in the nature of the work, physically impossible to perform differently.

- Discretionary Dependencies (Soft Logic): Defined by the project team based on best practices or preferences.

- External Dependencies: Relationships between project and non-project activities that are outside the project team's control.

- Internal Dependencies: Relationships between project activities that are within the project team's control.

How Activity Sequencing Works in CPM

1. Identify all project activities from the Work Breakdown Structure (WBS).

2. Determine dependencies between activities by asking:
- What must happen before this activity can start?
- What can happen only after this activity is complete?
- What can happen concurrently with this activity?

3. Create a network diagram showing the logical flow of activities.

4. Assign durations to each activity.

5. Calculate the forward and backward pass to determine early start, early finish, late start, and late finish dates.

6. Identify the critical path (the longest path through the network with zero float).

7. Calculate float/slack for non-critical activities.

Methods for Representing Dependencies:

- Arrow Diagramming Method (ADM): Activities are represented on arrows, with nodes representing events.

- Precedence Diagramming Method (PDM): Activities are represented in boxes (nodes), with arrows showing dependencies.

Advanced Concepts in Dependencies:

- Lead and Lag Time: Lead allows an acceleration of the successor activity, while lag introduces a delay.

- Constraint Dates: Imposed dates that restrict when an activity can start or finish.

- Multiple Predecessors/Successors: Activities often have relationships with multiple other activities.

Exam Tips: Answering Questions on Activity Sequencing and Dependencies in CPM

1. Understand the terminology: Be clear about the different types of dependencies (FS, SS, FF, SF) and their meanings.

2. Practice drawing network diagrams: Many exam questions will ask you to create or interpret network diagrams.

3. Know how to calculate: Be prepared to determine early/late start/finish dates and identify the critical path.

4. Identify float correctly: Understanding total float vs. free float is essential for many questions.

5. Recognize dependency impacts: Understand how changes in one activity's duration affect other activities and the overall schedule.

6. Apply leads and lags appropriately: Know when and how to use these schedule modifications.

7. Analyze scenario-based questions: Practice applying your knowledge to real-world project scenarios.

8. Watch for tricky wording: Pay attention to whether a question is asking about predecessor or successor relationships.

9. Remember the difference between mandatory and discretionary dependencies: This distinction often appears in exam questions.

10. Consider resource constraints: Some questions may incorporate resource availability into dependency decisions.

Common Exam Question Types:

- Creating a network diagram from a list of activities and dependencies
- Identifying the critical path in a given network
- Calculating float for specific activities
- Determining the impact of delays or accelerations
- Applying different types of dependencies to scenario-based questions
- Analyzing the effect of adding leads or lags
- Distinguishing between mandatory and discretionary dependencies

Final Advice:

When tackling exam questions on activity sequencing and dependencies in CPM, take your time to carefully read the question. Draw out the network diagram if it helps visualize the relationships. Double-check your calculations for early/late start/finish dates and float. Remember that the critical path has zero float and determines the project duration. Practice working with different dependency types and understand their practical applications in project scheduling.

Test mode:
Go Premium

PMI Scheduling Professional Preparation Package (2025)

  • 3429 Superior-grade PMI Scheduling Professional practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PMI-SP preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Activity Sequencing and Dependencies in CPM questions
12 questions (total)