Dependency Determination and Types in CPM

5 minutes 5 Questions

In the context of the Critical Path Method (CPM), defining and analyzing dependencies between project activities is a fundamental step in constructing an accurate project schedule. Dependencies dictate the sequence in which tasks are performed and influence the timing relationships between activities. Properly identifying and implementing dependencies ensures logical workflow and allows for effective management of project timelines. There are four primary types of activity dependencies: 1. **Finish-to-Start (FS)**: The successor activity cannot start until the predecessor activity has finished. This is the most common dependency type and represents a typical sequential relationship. For example, you cannot begin painting a wall (successor) until the wall has been constructed (predecessor). 2. **Start-to-Start (SS)**: The successor activity cannot start until the predecessor activity has started. This dependency is used when two activities can occur in parallel after both have begun. For instance, once design work starts, coding can commence, allowing for overlapping work. 3. **Finish-to-Finish (FF)**: The successor activity cannot finish until the predecessor activity has finished. This relationship is used when the completion of one task is contingent upon the completion of another. For example, editing a document cannot be completed until writing the document is finished. 4. **Start-to-Finish (SF)**: The successor activity cannot finish until the predecessor activity has started. This is the least common type and is used in scenarios where the successor must continue until the predecessor begins. An example might be a night shift guard (successor) cannot finish duty until the day shift guard (predecessor) arrives. Dependencies can also be categorized based on their nature: - **Mandatory Dependencies**: These are inherent in the nature of the work and are often contractually or physically required. They represent hard logic. For example, you must receive approval before you can proceed with procurement. - **Discretionary Dependencies**: Also known as soft logic, these are defined by project teams based on best practices or preferences. They offer flexibility in sequencing and can be adjusted to compress schedules if necessary. - **External Dependencies**: Dependencies that involve relationships between project activities and non-project activities, which are outside the project team's control. For example, waiting for government permits. Understanding and accurately modeling these dependencies is crucial for constructing the project’s schedule network diagram. It ensures activities are logically sequenced, resource allocations are optimized, and potential scheduling conflicts are minimized. Dependencies affect the calculation of early start (ES), early finish (EF), late start (LS), and late finish (LF) dates during the forward and backward pass techniques in CPM. Incorrect dependency determination can lead to flawed critical path identification, resulting in schedule delays, resource bottlenecks, and cost overruns. Effective dependency management enhances project control by providing clarity on task relationships, facilitating communication among stakeholders, and allowing for proactive risk management. It enables project managers to foresee the impact of changes in one activity on the rest of the schedule and adjust plans accordingly to maintain project objectives.

Test mode:
PMI-SP - Critical Path Method (CPM) Example Questions

Test your knowledge of Amazon Simple Storage Service (S3)

Question 1

In a Critical Path Method (CPM) analysis, what best describes a mandatory dependency (also known as hard logic)?

Question 2

Which of the following best describes a logical relationship in a CPM network where one activity must be delayed by a specific duration after another activity starts?

Question 3

In a Critical Path Method (CPM) network diagram, which statement best describes a Finish-to-Start (FS) dependency relationship?

Go Premium

PMI Scheduling Professional Preparation Package (2024)

  • 3429 Superior-grade PMI Scheduling Professional practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PMI-SP preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Dependency Determination and Types in CPM questions
12 questions (total)