Dependency Determination and Types in CPM Scheduling
In Critical Path Method (CPM) scheduling, determining task dependencies is fundamental to constructing an accurate project schedule. Dependencies define how tasks relate to one another and establish the sequence of activities. There are four primary types of dependencies in CPM scheduling: 1. **Finish-to-Start (FS)**: The most common dependency where a successor task cannot begin until its predecessor task has finished. For example, painting cannot start until surface preparation is complete. 2. **Start-to-Start (SS)**: A task cannot start until its predecessor has started. This allows two activities to begin simultaneously or with a delay defined by a lag. For instance, programming can start once design has started. 3. **Finish-to-Finish (FF)**: A task cannot finish until its predecessor has finished. This is useful when two activities must conclude together. For example, quality assurance must finish when testing concludes. 4. **Start-to-Finish (SF)**: The least common dependency where a task cannot finish until its predecessor has started. This might occur in scenarios like shift changes where the new shift must begin before the previous one can end. Understanding these dependencies is crucial for accurate schedule development. It ensures that tasks are sequenced logically and resources are allocated efficiently. Dependencies can be further classified as **mandatory**, **discretionary**, or **external**: - **Mandatory Dependencies**: Inherent in the nature of the work, such as legal or physical constraints. For example, concrete must cure before formwork is removed. - **Discretionary Dependencies**: Defined by the project team based on best practices or preferences. For instance, choosing to complete all design work before starting construction, even if some construction activities could technically begin earlier. - **External Dependencies**: Involve relationships between project tasks and external events or activities outside the project's control, such as regulatory approvals or delivery of materials from a supplier. Proper dependency determination helps identify the critical path accurately, assess project risks, and develop realistic schedules. It allows project managers to anticipate potential delays and implement mitigation strategies. Misidentifying dependencies can lead to scheduling conflicts, resource overallocation, and inaccurate timelines, adversely affecting project outcomes.
PMI-SP - Critical Path Method (CPM) Example Questions
Test your knowledge of Amazon Simple Storage Service (S3)
Question 1
According to PMI scheduling standards, which dependency type best describes when an activity's completion allows the start of its successor, but the successor can also begin earlier with an overlap?
Question 2
In CPM scheduling, what determines a Finish-to-Start (FS) mandatory dependency between two construction activities?
Question 3
In CPM scheduling, which type of dependency would best reflect a requirement where an activity must maintain a constant time interval of 5 days ahead of its successor throughout their durations?
Go Premium
PMI Scheduling Professional Preparation Package (2024)
- 3429 Superior-grade PMI Scheduling Professional practice questions.
- Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
- Unlock Effortless PMI-SP preparation: 5 full exams.
- 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
- Bonus: If you upgrade now you get upgraded access to all courses
- Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!