Forward and Backward Pass

5 minutes 5 Questions

The Forward and Backward Pass are techniques used in the Critical Path Method (CPM) to calculate the earliest and latest start and finish times for all activities in a project schedule. These calculations are essential for determining the project's duration, identifying the critical path, and calcu…

Test mode:
PMI-SP - Forward and Backward Pass Example Questions

Test your knowledge of Forward and Backward Pass

Question 1

During a forward and backward pass calculation in network diagramming, you discover that your project has a total float of 5 days and a free float of 3 days on a critical activity. What does this indicate?

Question 2

When performing a forward and backward pass calculation, you notice that an activity has an early start (ES) of Day 5 and a late start (LS) of Day 10. What important project information does this reveal?

Question 3

During a network analysis, you notice that the forward pass calculation yields an early finish (EF) of Day 15, while the backward pass shows a late finish (LF) of Day 15 for Activity C. What characteristic does this indicate about Activity C?

More Forward and Backward Pass questions
12 questions (total)