Forward Pass and Backward Pass Calculations

5 minutes 5 Questions

Forward Pass and Backward Pass calculations are essential analytical techniques used in the Critical Path Method (CPM) to determine the earliest and latest start and finish times for each activity within a project schedule. These calculations are fundamental for identifying the critical path and ca…

Test mode:
PMI-SP - Forward Pass and Backward Pass Calculations Example Questions

Test your knowledge of Forward Pass and Backward Pass Calculations

Question 1

When performing Forward Pass calculations in a network diagram with three parallel paths where Activity D has an Early Start (ES) of 10 and Duration of 5 days, what determines the Early Finish (EF) for Activity D?

Question 2

In a network diagram, Activity Y has three predecessor activities with Early Finish (EF) times of 15, 22, and 18 days respectively. Which principle determines Activity Y's Early Start (ES)?

Question 3

In a critical path calculation, if Activity Z has an Early Start (ES) of 12 days, Early Finish (EF) of 20 days, Late Start (LS) of 15 days, and Late Finish (LF) of 23 days, what is its Total Float (TF)?

More Forward Pass and Backward Pass Calculations questions
9 questions (total)