Lead and Lag Times and Their Effect on the Critical Path

5 minutes 5 Questions

Lead and lag times are essential components in the Critical Path Method (CPM) that allow project managers to fine-tune activity relationships and model real-world scheduling scenarios more accurately. By adjusting the timing of successor activities relative to their predecessors, leads and lags pro…

Test mode:
PMI-SP - Lead and Lag Times and Their Effect on the Critical Path Example Questions

Test your knowledge of Lead and Lag Times and Their Effect on the Critical Path

Question 1

In a project schedule network diagram, Activity B has a lag time of 3 days with its successor Activity C, while Activity D has a lead time of 2 days with Activity E. What is the correct interpretation of these relationships?

Question 2

During schedule network analysis, a project manager applies a 5-day lag to a critical path activity that has a successor with a finish-to-start relationship. What effect does this have on the project schedule?

Question 3

A project manager needs to add both lead and lag times to parallel activities. Which statement accurately describes how these time adjustments affect the critical path calculation?

More Lead and Lag Times and Their Effect on the Critical Path questions
12 questions (total)