Leads and Lags in Critical Path Method
Leads and lags are essential tools in the Critical Path Method (CPM) for refining the schedule by adjusting the timing between dependent tasks. They provide flexibility in modeling the realistic flow of activities beyond the basic dependency types. - **Lead**: An acceleration of the successor task. It allows the successor activity to start before the predecessor activity has fully completed. For example, in a Finish-to-Start dependency with a lead of 2 days, the successor task begins 2 days before the predecessor task finishes. This is useful when tasks can overlap, such as starting the installation of equipment before all the wiring is complete. - **Lag**: A delay between the predecessor and successor tasks. It introduces a waiting period after the predecessor task before the successor can begin. For instance, in a Finish-to-Start dependency with a lag of 3 days, there is a 3-day gap after the predecessor finishes before the successor starts. Lags are commonly used to represent waiting times, such as curing periods for concrete or delivery times for materials. Incorporating leads and lags enhances the schedule's accuracy by reflecting the actual conditions and constraints of the project. It allows project managers to model concurrent activities and account for necessary delays without adding unnecessary tasks to the schedule. However, the use of leads and lags requires careful consideration: - **Documentation**: Every lead and lag should be clearly documented with justifications to ensure transparency and understanding among stakeholders. - **Impact on Critical Path**: Leads and lags can affect the critical path by altering task start and finish dates. Misuse can obscure the true critical path and complicate schedule analysis. - **Risk Management**: Excessive use of leads and lags can introduce risks due to increased complexity. It is important to assess whether the benefits outweigh potential scheduling uncertainties. By effectively utilizing leads and lags, project managers can optimize the schedule, improve resource utilization, and enhance the likelihood of meeting project deadlines. It allows for a more dynamic and responsive project plan that can adapt to the realities of project execution.
Leads and Lags in Critical Path Method (CPM)
What are Leads and Lags in CPM?
Leads and lags are time modifications applied to task dependencies in the Critical Path Method. A lead allows an acceleration of the successor activity by starting it before its predecessor finishes. A lag introduces a delay between the end of a predecessor and the start of a successor activity.
Why are Leads and Lags Important?
Leads and lags are crucial in project scheduling because they:
- Reflect real-world timing relationships between activities
- Optimize schedules by allowing appropriate overlaps or required delays
- Provide flexibility in resource allocation
- Allow for technical constraints in project execution
- Help create more accurate and achievable project timelines
How Leads and Lags Work in CPM
1. Leads (Negative Lag):
- Expressed as negative values (e.g., FS-5 means a 5-day lead)
- Enable partial overlapping of activities
- Example: Starting painting when 75% of drywall is complete, not waiting for 100% completion
2. Lags (Positive Lag):
- Expressed as positive values (e.g., FS+3 means a 3-day lag)
- Create mandatory waiting periods between activities
- Example: Waiting 48 hours for concrete to cure before continuing construction
3. Dependency Types with Leads/Lags:
- Finish-to-Start (FS): Most common; successor starts after predecessor finishes
- Start-to-Start (SS): Successor starts after predecessor starts
- Finish-to-Finish (FF): Successor finishes after predecessor finishes
- Start-to-Finish (SF): Successor finishes after predecessor starts
Network Diagram Representation:
Leads and lags are typically shown as labels on dependency arrows in network diagrams, often with positive or negative values indicating duration.
Impact on Critical Path Calculation:
- Leads can potentially shorten the critical path
- Lags can extend the critical path
- Both affect float calculations for activities
Exam Tips: Answering Questions on Leads and Lags in CPM
1. Know the Terminology:
- Understand the clear distinction between leads and lags
- Remember that leads represent acceleration (negative lag)
- Remember that lags represent delays (positive lag)
2. Calculate Schedule Impacts:
- Practice calculating how leads and lags affect Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) dates
- Be prepared to recalculate the critical path when leads or lags are modified
3. Watch for Context Clues:
- In scenario-based questions, identify whether the situation calls for a lead or lag
- Look for phrases like "must wait 3 days after" (lag) or "can start when predecessor is 50% complete" (lead)
4. Common Question Types:
- Network diagram interpretation with leads/lags
- Schedule compression opportunities using leads
- Critical path identification with various leads and lags
- Float calculations affected by leads/lags
5. Potential Pitfalls:
- Pay attention to whether leads/lags are expressed in days, hours, or another time unit
- Verify which dependency type (FS, SS, FF, SF) the lead/lag applies to
- Be careful with the sign convention (negative for leads, positive for lags)
6. Apply Professional Judgment:
- Understand that exam questions may test your ability to determine when leads or lags are appropriate
- Consider technical requirements, resource constraints, and risks when evaluating lead/lag scenarios
7. Remember the PDM Connection:
- Leads and lags are integral to Precedence Diagramming Method (PDM)
- Know how they interact with all four dependency types
Understanding leads and lags thoroughly will help you optimize project schedules, pass certification exams, and apply CPM effectively in real-world project management settings.
Go Premium
PMI Scheduling Professional Preparation Package (2025)
- 3429 Superior-grade PMI Scheduling Professional practice questions.
- Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
- Unlock Effortless PMI-SP preparation: 5 full exams.
- 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
- Bonus: If you upgrade now you get upgraded access to all courses
- Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!