PMI-SP - Critical Path Method (CPM) - Resource Leveling and Its Impact on the Critical Path
Expert
1/12
When performing resource leveling in a schedule network with parallel paths, what happens to resource utilization peaks if both critical and near-critical activities share the same resource pool?
a.
Resource peaks increase while project duration remains constant due to parallel path compression techniques
b.
Resource peaks remain unchanged but project duration decreases due to enhanced resource optimization across parallel paths
c.
Resource peaks and project duration both decrease due to improved resource distribution across multiple activity paths
d.
Resource peaks decrease while total project duration may increase due to sequential scheduling
Expert