Schedule Network Diagram Construction

5 minutes 5 Questions

The Schedule Network Diagram is a fundamental tool in the Critical Path Method (CPM) used for visualizing the sequence and interdependencies of all activities in a project. It provides a graphical representation of the project's activities, showcasing how each task is connected based on dependencie…

Test mode:
PMI-SP - Schedule Network Diagram Construction Example Questions

Test your knowledge of Schedule Network Diagram Construction

Question 1

Which technique is most appropriate when constructing a schedule network diagram for activities with complex interdependencies?

Question 2

When establishing the Schedule Network Diagram sequence flow, what represents the most appropriate way to handle two parallel activities that must finish at exactly the same time?

Question 3

When creating a Schedule Network Diagram, what is the recommended approach for handling multiple paths that converge at a single milestone?

More Schedule Network Diagram Construction questions
12 questions (total)