PMI-SP - Critical Path Method (CPM) - Schedule Network Diagram Construction
Expert
1/5
In a Schedule Network Diagram, what is the most suitable method for handling merged paths with overlapping resource constraints?
a.
Apply resource leveling to combined paths before finalizing network dependencies
b.
Create separate network segments for each resource-constrained path and establish lag relationships between them
c.
Analyze each path individually and assign priority based on critical path calculations and resource availability
d.
Implement a buffer zone at each merging point and adjust the network paths based on total float calculations