Estimating Activity Durations
Estimating Activity Durations is a critical concept in defining schedule objectives. It involves determining the amount of time required to complete each activity within a project. Accurate duration estimates are essential for developing a realistic and achievable project schedule. These estimates are based on various factors, including the nature of the work, resource availability, skill levels, and potential risks or uncertaintiesThere are several techniques for estimating activity durations, such as expert judgment, analogous estimating, parametric estimating, three-point estimating, and bottom-up estimating. Expert judgment relies on the experience of individuals who have performed similar tasks in the past. Analogous estimating uses historical data from similar projects to predict durations. Parametric estimating involves statistical relationships between historical data and variables (e.g., cost per square foot). Three-point estimating considers optimistic, most likely, and pessimistic scenarios to account for uncertainty. Bottom-up estimating aggregates estimates of smaller components to form a total durationAccurate estimation helps in setting realistic expectations with stakeholders, managing resource allocation effectively, and identifying potential schedule risks early in the planning process. It also plays a vital role in critical path analysis, as incorrect durations can lead to an inaccurate critical path, affecting the overall project timeline. Additionally, duration estimates should be continuously refined as the project progresses and more information becomes available. Regular reviews and adjustments ensure that the schedule remains relevant and achievableIn summary, Estimating Activity Durations is about predicting the time each task will take, using various methods to ensure accuracy. It is foundational for creating a viable schedule, allocating resources appropriately, and managing stakeholder expectations. Being proficient in this concept enables project managers to develop schedules that are both realistic and flexible enough to accommodate changes and unforeseen challenges.
Estimating Activity Durations: A Comprehensive Guide for PMI-SP Exam
Why Estimating Activity Durations is Important
Estimating activity durations is a critical component of schedule management because:
• It forms the foundation for creating a realistic project schedule
• It determines when activities can start and finish
• It influences resource allocation and costs
• It helps identify the critical path
• It enables accurate timeline commitments to stakeholders
• It provides a baseline for monitoring progress and performance
What is Activity Duration Estimation?
Activity duration estimation is the process of approximating the number of work periods needed to complete individual activities with the estimated resources. It answers the question: "How long will each task take to complete?"
Duration estimates are:
• Expressed in work periods (hours, days, weeks, months)
• Based on the effort required and resources available
• Progressive elaborations that become more accurate as the project progresses
• Different from effort estimates (person-hours), which may not translate directly to duration
How Activity Duration Estimation Works
Inputs:
• Activity list from the activity definition process
• Resource requirements and availability
• Historical information and organizational process assets
• Resource calendars
• Project scope statement
• Risk register
• Resource breakdown structure
• Enterprise environmental factors
Techniques:
1. Expert Judgment: Using experience of subject matter experts
2. Analogous Estimating: Using durations from similar activities in previous projects
• Fast but less accurate
• Useful when limited information is available
• Top-down approach
3. Parametric Estimating: Using mathematical models based on historical data and parameters
• Example: 2 hours per module × 10 modules = 20 hours
• Can be very accurate if parameters are solid
4. Three-Point Estimates: Using weighted average of optimistic, most likely, and pessimistic estimates
• PERT formula: (O + 4M + P) ÷ 6
• Triangular Distribution: (O + M + P) ÷ 3
• Accounts for uncertainty and risk
5. Bottom-up Estimating: Breaking activities into smaller components, estimating each, then aggregating
• Most accurate but time-consuming
• Used for high-risk or complex activities
6. Reserve Analysis: Adding contingency reserves to account for schedule risk
7. Group Decision-Making Techniques: Using methods like Delphi, nominal group technique, etc.
Outputs:
• Activity duration estimates
• Basis of estimates (assumptions, constraints, ranges)
• Updates to project documents
Common Challenges in Duration Estimating
• Student Syndrome: Delaying work until the deadline approaches
• Parkinson's Law: Work expanding to fill the time available
• Padding: Adding extra time as hidden contingency
• Optimism bias: Underestimating complexity and risks
• Multitasking inefficiencies: Context switching costs
• Inadequate historical data: Making comparisons difficult
Best Practices for Accurate Duration Estimates
• Involve the people who will do the work
• Consider resource skill levels and experience
• Account for resource availability and productivity factors
• Use multiple estimation techniques for comparison
• Document assumptions and constraints
• Update estimates as more information becomes available
• Review and learn from past estimation accuracy
• Consider communication and coordination overhead
• Build in appropriate (but transparent) reserves
Exam Tips: Answering Questions on Estimating Activity Durations
1. Know the PMBOK terminology:
• Understand the difference between duration, effort, and elapsed time
• Distinguish between activity durations and milestone dates
2. Identify the appropriate estimation technique:
• Look for clues about available information (historical data, parameters, experts)
• Consider project phase and estimation purpose
3. Calculate using formulas correctly:
• Be prepared to apply PERT formulas: (O + 4M + P) ÷ 6
• Know how to convert effort hours to duration based on resources
4. Recognize estimation pitfalls:
• Be alert for questions about estimation bias and how to address it
• Understand when padding is inappropriate versus when contingency is appropriate
5. Remember the inputs and outputs:
• Know what information is needed for good estimates
• Understand how duration estimates feed into schedule development
6. Apply situational judgment:
• For scenario questions, consider the project context, constraints, and objectives
• Assess the impact of risks on duration estimates
7. Identify the role of historical information:
• Historical information influences all estimation techniques
• Lessons learned impact how you should approach estimation
Remember that for PMI-SP exam questions, you'll need to identify not just what you could do, but what you should do as a scheduling professional following PMI standards. Focus on selecting answers that demonstrate sound judgment and adherence to best practices in schedule management.
Go Premium
PMI Scheduling Professional Preparation Package (2025)
- 3429 Superior-grade PMI Scheduling Professional practice questions.
- Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
- Unlock Effortless PMI-SP preparation: 5 full exams.
- 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
- Bonus: If you upgrade now you get upgraded access to all courses
- Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!