Estimating Activity Durations

5 minutes 5 Questions

Estimating Activity Durations is a critical concept in defining schedule objectives. It involves determining the amount of time required to complete each activity within a project. Accurate duration estimates are essential for developing a realistic and achievable project schedule. These estimates …

Test mode:
PMI-SP - Estimating Activity Durations Example Questions

Test your knowledge of Estimating Activity Durations

Question 1

You have been tasked with managing a project that involves manufacturing a large quantity of a new product. You want to estimate the total time needed based on the time required to produce a single unit. What technique would you likely use?

Question 2

You are supervising an IT project. You have schedules for each programming task but these tasks are quite similar. What estimation technique suits this situation?

Question 3

You're managing a project with unfamiliar activities. An expert suggested the use of an estimation technique that uses weighted averages of optimistic, pessimistic, and most likely estimates. What technique is he suggesting?

More Estimating Activity Durations questions
36 questions (total)