Resource Allocation and Leveling

5 minutes 5 Questions

Resource Allocation and Leveling is a key concept in defining schedule objectives, focusing on the efficient and effective distribution of resources to project activities. This involves assigning available resources—such as personnel, equipment, or materials—to tasks in a way that meets project objectives while considering constraints like availability, skill sets, and workload balanceResource Allocation ensures that resources are assigned to the right tasks at the right time. It requires an understanding of each resource's capacity and the demands of each activity. Proper allocation avoids over-allocation, where a resource is expected to do more work than is feasible in a given time frame, and under-allocation, which can lead to resource idle time and increased costsResource Leveling is the process of smoothing out the resource allocation over the project timeline to avoid peaks and troughs in resource usage. It often involves adjusting the start and finish dates of activities based on resource constraints. The goal is to minimize periods of resource shortage or surplus, ensuring a consistent workload and preventing burnout or underutilization of resourcesEffective Resource Allocation and Leveling contribute to a realistic and achievable project schedule. They help in identifying potential bottlenecks, enhancing team productivity, and reducing costs associated with resource inefficiencies. This concept also supports risk management by highlighting areas where resource issues could impact project timelinesTools like Gantt charts and resource histograms are often used to visualize resource allocation and identify conflicts. Software applications can assist in automating these processes, especially in complex projects with numerous resources and interdependenciesIn essence, Resource Allocation and Leveling aim to optimize the use of resources to meet project objectives efficiently. By carefully planning and adjusting resource assignments, project managers can ensure that the project schedule is practical and that resources are used effectively throughout the project lifecycle.

Resource Allocation and Leveling: A Comprehensive Guide

Why Resource Allocation and Leveling is Important

Resource allocation and leveling are critical components of project scheduling that ensure projects are completed efficiently and effectively. These processes are important because:

• They help prevent resource overallocation which can lead to burnout, decreased productivity, and poor quality work
• They ensure optimal use of available resources
• They contribute to more realistic and achievable project schedules
• They help identify and resolve resource conflicts early
• They support cost control by efficiently distributing work

What is Resource Allocation and Leveling?

Resource allocation is the process of assigning specific resources to project activities based on their availability, capability, and capacity. This involves determining what resources are needed, when they are needed, and in what quantities.

Resource leveling is a technique that adjusts the start and finish dates of activities to address resource limitations or uneven resource usage. It aims to balance resource demand with resource supply while minimizing fluctuations in resource usage patterns.

How Resource Allocation Works:

1. Resource Identification: Determine what resources (people, equipment, materials) are required for each project activity

2. Resource Requirements Estimation: Calculate how much of each resource is needed and for how long

3. Resource Availability Assessment: Identify when resources are available and in what capacity

4. Resource Assignment: Match specific resources to activities based on skills, availability, and other criteria

5. Resource Calendar Creation: Develop calendars showing when resources are allocated to specific tasks

How Resource Leveling Works:

1. Identify Overallocations: Detect when resources are assigned more work than their capacity

2. Analyze Schedule Flexibility: Examine which activities have float/slack that allows for delay

3. Apply Leveling Techniques:
• Delaying activities using available float
• Splitting activities to allow resources to work on multiple tasks
• Adjusting resource assignments
• Extending activity durations

4. Evaluate Impact: Assess how leveling affects project duration, critical path, and deadlines

5. Optimize: Refine the leveled schedule to minimize negative impacts

Common Resource Leveling Techniques:

Time-constrained leveling: Maintains the project end date but may require additional resources

Resource-constrained leveling: Maintains resource limits but may extend project duration

Fast-tracking: Performing activities in parallel that would normally be done sequentially

Crashing: Adding resources to critical activities to reduce duration

Tools for Resource Allocation and Leveling:

• Resource histograms: Visual representations of resource usage over time
• Resource loading charts: Displays when specific resources are assigned to activities
• Project management software (Microsoft Project, Primavera P6, etc.)

Exam Tips: Answering Questions on Resource Allocation and Leveling

1. Understand the difference between allocation and leveling:
• Allocation = assigning resources to activities
• Leveling = adjusting the schedule to resolve resource conflicts

2. Know the impacts of resource constraints:
• Resource constraints often extend project duration
• The critical path may change after resource leveling

3. Recognize leveling priorities:
• Activities with float are typically delayed first
• Critical activities are usually protected from delays

4. Be familiar with resource histograms:
• Before leveling: May show overallocations (peaks above capacity)
• After leveling: Should show more consistent resource usage

5. Remember key formulas:
• Resource availability = (# of resources) × (hours per day) × (utilization factor)
• Duration with constrained resources often increases

6. Focus on trade-offs:
• Time vs. resource availability
• Cost vs. schedule impacts
• Quality vs. speed

7. Practice calculations:
• Resource demand calculations
• Impact of leveling on float
• New project duration after leveling

8. Look for context clues in exam questions:
• Is the project time-constrained or resource-constrained?
• What is the priority: finishing on time or not exceeding resource limits?

When faced with scenario-based questions, always analyze what the question is asking about: the allocation process, leveling techniques, or the impacts of resource constraints on the schedule.

Test mode:
PMI-SP - Defining Schedule Objectives Example Questions

Test your knowledge of Amazon Simple Storage Service (S3)

Question 1

During resource allocation planning, what is the most effective way to handle a skilled resource who is assigned to multiple critical path activities?

Question 2

When implementing resource leveling in a project schedule, what is the primary objective?

Question 3

In resource leveling, what technique is most appropriate when dealing with an overallocated resource who is working on parallel activities with varying float?

Go Premium

PMI Scheduling Professional Preparation Package (2025)

  • 3429 Superior-grade PMI Scheduling Professional practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PMI-SP preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Resource Allocation and Leveling questions
12 questions (total)