100% Rule

5 minutes 5 Questions

The 100% Rule is a critical principle in the development of a Work Breakdown Structure (WBS) that ensures completeness and clarity in project scope definition. It states that the WBS must capture all the work defined by the project scope, including all deliverables and activities, accounting for 10…

Test mode:
PMI-SP - 100% Rule Example Questions

Test your knowledge of 100% Rule

Question 1

In a project where the 100% Rule is applied to the WBS, what happens if a deliverable accounts for 90% of work at its level?

Question 2

When implementing the 100% Rule in WBS, which statement most accurately represents the internal consistency check?

Question 3

When should the 100% Rule validation be performed during the WBS development process?

More 100% Rule questions
14 questions (total)