PMI-SP - Developing the Work Breakdown Structure (WBS) - Decomposition Process
Expert
1/12
In the decomposition process for project scheduling, what outcome indicates that sufficient detail has been achieved?
a.
All activities have been broken down into one-hour increments of work
b.
Team members can estimate duration with reasonable accuracy
c.
Each work package has been assigned to a specific department or group
d.
The schedule network diagram shows complete path dependencies
Expert