PMI-SP - Developing the Work Breakdown Structure (WBS) - Decomposition Process
Beginner
1/5
In the context of project scheduling, what is the primary purpose of the decomposition process?
a.
To analyze and subdivide project tasks based on sequential dependencies and critical path methodologies
b.
To separate project activities according to their duration estimates and resource requirements in the network diagram
c.
To break down project deliverables into smaller, manageable work packages
d.
To break down project deliverables into smaller components while ensuring minimal resource allocation and maximum cost efficiency in the scheduling process
Beginner