PMI-SP - Documenting Lessons Learned - Facilitating Lessons Learned Sessions for Knowledge Sharing
Expert
1/5
What is the most effective way to structure the documentation output from a lessons learned session about project scheduling?
a.
Develop individual case studies for each major scheduling challenge and its mitigation strategy throughout the project
b.
Use a standardized template with categories for risks, successes, and schedule variances
c.
Create detailed narrative reports that describe each scheduling incident and its resolution in chronological order
d.
Maintain separate logs for each project phase with corresponding schedule performance metrics and team feedback
Expert