PMI-SP - Documenting Lessons Learned - Integrating Lessons Learned into Organizational Processes
Expert
1/5
What is the most effective process for incorporating scheduling lessons learned into an organization's standard practices?
a.
Establishing mandatory review sessions where project managers present their schedule management findings
b.
Developing extensive case studies from past projects and sharing them during training sessions
c.
Creating a comprehensive database of all project scheduling experiences and distributing quarterly reports
d.
Mapping lessons to specific process groups and updating relevant procedural templates
Expert