PMI-SP - Documenting Lessons Learned - Leveraging Technology Tools for Documenting Lessons Learned
Intermediate
1/12
When retrieving archived schedule data for a new project, what is the most important consideration for a project manager?
a.
The availability of complete resource allocation data from the archived schedule for current planning
b.
The age of the archived schedule data and its compliance with current organizational practices and standards
c.
The similarity of scope and objectives between the archived project and the new project
d.
The total number of activities and milestones present in the archived schedule that can be reused