Cost Performance Index (CPI)

5 minutes 5 Questions

The Cost Performance Index (CPI) is a key metric within Earned Value Management (EVM) that measures the cost efficiency of budgeted resources in a project. It is calculated by dividing the Earned Value (EV) by the Actual Cost (AC), represented as CPI = EV / AC. A CPI value greater than 1 indicates …

Test mode:
PMI-SP - Cost Performance Index (CPI) Example Questions

Test your knowledge of Cost Performance Index (CPI)

Question 1

In a large construction project, if the CPI is 1.2 and the SPI is 0.8, what best describes the project status?

Question 2

When calculating the Cost Performance Index (CPI) for earned value analysis, which formula produces the most accurate result?

Question 3

A project's Cost Performance Index (CPI) is 0.85. What does this indicate about the project's cost efficiency?

More Cost Performance Index (CPI) questions
12 questions (total)