Cost Variance (CV)

5 minutes 5 Questions

Cost Variance (CV) is a crucial metric in Earned Value Management (EVM) that quantifies the difference between the budgeted cost of work performed and the actual cost incurred for that work. It is calculated using the formula: CV = Earned Value (EV) minus Actual Cost (AC). CV provides insight into …

Test mode:
PMI-SP - Cost Variance (CV) Example Questions

Test your knowledge of Cost Variance (CV)

Question 1

When reviewing historical project data, which combination of values indicates the most serious Cost Variance (CV) issue?

Question 2

In a project's earned value analysis, if CV is -$5,000 at Week 12 and -$15,000 at Week 16, what probable scenario explains this pattern?

Question 3

If a project's Cost Variance (CV) at the 50% completion mark is $0, while Schedule Performance Index (SPI) is 0.8, what does this indicate about the project's performance?

More Cost Variance (CV) questions
24 questions (total)