Earned Value (EV)

5 minutes 5 Questions

Earned Value (EV) is a fundamental concept in Earned Value Management (EVM) that represents the value of work actually completed up to a specific point in time, expressed in terms of the authorized budget assigned to that work. It provides a quantifiable measure of project progress by integrating s…

Test mode:
PMI-SP - Earned Value (EV) Example Questions

Test your knowledge of Earned Value (EV)

Question 1

In a project experiencing cost overruns, what is the most accurate way to calculate Earned Value (EV) for a task that is 75% complete?

Question 2

In a project where the planned value (PV) is $500,000, which of the following statements accurately defines Earned Value (EV)?

Question 3

When determining Earned Value (EV) for a project activity that uses weighted milestones, how should the value be calculated?

More Earned Value (EV) questions
12 questions (total)