Earned Value (EV)

5 minutes 5 Questions

Earned Value (EV) is a fundamental concept in Earned Value Management (EVM) that represents the value of work actually completed up to a specific point in time, expressed in terms of the authorized budget assigned to that work. It provides a quantifiable measure of project progress by integrating scope, schedule, and cost parameters. EV enables project managers to objectively assess how much of the planned work has been accomplished, allowing for a direct comparison with both the planned value and actual costs. In practice, EV is calculated by determining the percentage of completed work for each activity or task and multiplying it by the budgeted cost for that activity. For example, if a task budgeted at $10,000 is 50% complete, the EV for that task is $5,000. Summing the EVs of all completed work provides an aggregate measure of progress for the project. EV is crucial for analyzing variances in project performance. By comparing EV to Planned Value (PV), which represents the expected value of work planned to be completed by a certain date, project managers can calculate the Schedule Variance (SV) to determine if the project is ahead or behind schedule. Similarly, comparing EV to Actual Cost (AC) allows for the calculation of Cost Variance (CV), indicating whether the project is under or over budget. Understanding and utilizing EV empowers project managers to make informed decisions, implement corrective actions, and forecast future project performance. It shifts the focus from merely tracking expenditures to evaluating the value generated by those expenditures, fostering a more effective and proactive approach to project management. In essence, Earned Value serves as the backbone of EVM by providing a comprehensive metric that reflects true project performance across multiple dimensions.

Earned Value (EV): Understanding Its Importance and Application

What is Earned Value (EV)?

Earned Value (EV) is a critical project management metric that measures the value of work actually completed at a specific point in time. It represents the approved budget for the work that has been physically accomplished. Also known as the Budgeted Cost of Work Performed (BCWP), EV helps project managers understand if a project is progressing as planned in terms of schedule and budget.

Why is Earned Value Important?

Earned Value is essential in project management for several reasons:

1. Objective Progress Measurement: EV provides an objective way to measure project progress rather than relying on subjective assessments.

2. Early Warning System: It serves as an early warning system for potential project issues, allowing for corrective actions before problems escalate.

3. Integration of Scope, Schedule, and Cost: EV integrates these three fundamental project dimensions into one measurement system.

4. Decision Support: It provides quantitative data for making informed project decisions.

5. Forecasting Capability: EV helps predict future project performance and outcomes.

How Earned Value Works

Calculating EV follows this formula:

EV = % Complete × Budget at Completion (BAC)

For example, if a project has a total budget (BAC) of $100,000 and is 30% complete, the Earned Value is:

EV = 30% × $100,000 = $30,000

This means that $30,000 worth of work has been actually completed based on the original budget.

EV can also be calculated for individual work packages or deliverables and then summed up for the entire project.

EV in the Context of Earned Value Management (EVM)

EV is just one component of Earned Value Management (EVM), which also includes:

- Planned Value (PV): The authorized budget assigned to scheduled work.

- Actual Cost (AC): The actual costs incurred for the work performed.

Using these three values (EV, PV, AC), project managers can derive various performance indices and variances to assess project health.

Exam Tips: Answering Questions on Earned Value (EV)

1. Know the Formula: Memorize that EV = % Complete × BAC. This is fundamental.

2. Understand the Relationship: Be clear on how EV relates to other EVM metrics like PV and AC.

3. Interpret Schedule Variance (SV): Remember that SV = EV - PV, and a positive value indicates the project is ahead of schedule.

4. Interpret Cost Variance (CV): CV = EV - AC, and a positive value means the project is under budget.

5. Apply the Indices: Know that Schedule Performance Index (SPI) = EV/PV and Cost Performance Index (CPI) = EV/AC.

6. Look for Keywords: In exam questions, look for terms like "value of work performed," "completed work value," or "BCWP" as indicators that the question is asking about EV.

7. Consider Units: EV is always expressed in monetary units, not percentages or time units.

8. Context Matters: Consider the project context when interpreting EV. A high EV might seem good but could indicate scope creep if not planned.

9. Practice Calculations: Work through sample problems to become comfortable with EV calculations.

10. Connect to Project Outcomes: Be prepared to explain how EV impacts project outcomes and decision-making.

Real-World Application

Project managers use EV to:

- Report project status to stakeholders
- Make data-driven decisions about resource allocation
- Forecast final costs and completion dates
- Identify trends and patterns in project performance
- Justify requests for additional resources or time

By mastering the concept of Earned Value, project managers gain a powerful tool for keeping projects on track and ensuring successful delivery within constraints.

Test mode:
Go Premium

PMI Scheduling Professional Preparation Package (2025)

  • 3429 Superior-grade PMI Scheduling Professional practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PMI-SP preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Earned Value (EV) questions
12 questions (total)