Schedule Variance (SV)
Schedule Variance (SV) is an essential component of Earned Value Management (EVM) that quantifies the difference between the work actually completed and the work planned to be completed at a given point in time. It is calculated by subtracting the Planned Value (PV) from the Earned Value (EV), expressed as SV = EV - PV. A positive SV indicates that a project is ahead of schedule, accomplishing more work than planned. A negative SV signifies that a project is behind schedule, and an SV of zero indicates the project is exactly on schedule. SV is crucial because it provides a monetary representation of schedule performance, allowing project managers to understand schedule deviations in financial terms. This aids in making informed decisions regarding resource reallocation, schedule adjustments, and implementing corrective actions to realign the project timeline. By analyzing SV, project managers can identify schedule slippages early, understand their impact on the project budget and timeline, and take necessary measures to mitigate risks. It also helps in forecasting the project's future schedule performance and completion date, enabling better planning and communication with stakeholders. Schedule Variance is often used in conjunction with the Schedule Performance Index (SPI) to provide a comprehensive picture of schedule performance. While SV provides the absolute value of schedule deviation, SPI offers a relative measure of schedule efficiency. Together, they enable project managers to analyze trends over time and assess the effectiveness of schedule management strategies. It's important to note that SV can sometimes be misleading in projects with non-linear spending patterns. Therefore, SV should be interpreted carefully, considering the project's context and supplemented with additional analysis when necessary.
Schedule Variance (SV) in Earned Value Management
What is Schedule Variance (SV)?
Schedule Variance (SV) is a critical metric in Earned Value Management (EVM) that measures project schedule performance by comparing the work completed against the work planned. It tells project managers whether a project is ahead of schedule, on schedule, or behind schedule.
The formula for Schedule Variance is:
SV = EV - PV
Where:
• EV (Earned Value) is the value of work actually completed
• PV (Planned Value) is the value of work scheduled to be completed
Interpreting Schedule Variance:
• Positive SV (SV > 0): Project is ahead of schedule
• Zero SV (SV = 0): Project is on schedule
• Negative SV (SV < 0): Project is behind schedule
Why Schedule Variance is Important
Schedule Variance provides several key benefits to project management:
1. Early Warning System: SV helps identify schedule slippages early, allowing for timely corrective actions
2. Quantitative Measurement: It provides an objective, monetary value to schedule performance rather than subjective assessments
3. Trend Analysis: Tracking SV over time reveals whether schedule performance is improving or deteriorating
4. Communication Tool: SV offers a clear, standardized way to communicate schedule status to stakeholders
5. Integration with Cost: Works alongside Cost Variance (CV) to give a complete picture of project health
How Schedule Variance Works in Practice
Let's consider an example:
A project task has a budget of $10,000 and is scheduled to be 50% complete by the status date. The actual work shows it's only 40% complete.
PV = $10,000 × 50% = $5,000
EV = $10,000 × 40% = $4,000
SV = $4,000 - $5,000 = -$1,000
The negative SV of $1,000 indicates the project is behind schedule, specifically by the equivalent of $1,000 worth of work.
Schedule Variance Percentage (SV%)
For easier comparison across projects, SV can be expressed as a percentage:
SV% = (SV ÷ PV) × 100%
In our example:
SV% = (-$1,000 ÷ $5,000) × 100% = -20%
This means the project is 20% behind schedule relative to what was planned.
Limitations of Schedule Variance
1. SV is expressed in monetary terms, not time units, which can sometimes be confusing
2. SV tends to converge to zero at project completion even if the project finished late
3. SV doesn't account for the critical path, so it may not reflect the true impact on project completion date
Schedule Performance Index (SPI)
SV is often used alongside Schedule Performance Index (SPI), which is calculated as:
SPI = EV ÷ PV
• SPI > 1: Ahead of schedule
• SPI = 1: On schedule
• SPI < 1: Behind schedule
For our example:
SPI = $4,000 ÷ $5,000 = 0.8
This indicates the project is progressing at 80% of the planned rate.
Exam Tips: Answering Questions on Schedule Variance (SV)
1. Memorize the Formula: Know that SV = EV - PV. Many exam questions require quick application of this formula.
2. Understand the Interpretation: Be clear about what positive, negative, and zero values mean for schedule performance.
3. Practice Calculations: Work through sample problems where you calculate SV from given EV and PV values.
4. Connect with Other Metrics: Understand how SV relates to SPI, CV, CPI, and other EVM metrics.
5. Remember Units: SV is always expressed in currency units (dollars, euros, etc.), not in time units.
6. Look for Trend Questions: Exams may ask about interpreting SV trends over the project lifecycle.
7. Watch for Scenarios: Some questions present a project scenario and ask you to determine if the project is ahead or behind schedule based on SV.
8. Consider Corrective Actions: Be prepared for questions about appropriate corrective actions based on SV results.
9. Distinguish from CV: Don't confuse Schedule Variance (SV) with Cost Variance (CV = EV - AC).
10. Cumulative vs. Period Values: Understand that SV can be calculated for a specific period or cumulatively for the project to date.
By mastering Schedule Variance calculations and interpretations, you'll be well-equipped to answer EVM questions on your PMI-SP or other project management certification exams.
Go Premium
PMI Scheduling Professional Preparation Package (2025)
- 3429 Superior-grade PMI Scheduling Professional practice questions.
- Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
- Unlock Effortless PMI-SP preparation: 5 full exams.
- 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
- Bonus: If you upgrade now you get upgraded access to all courses
- Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!