Schedule Variance (SV)

5 minutes 5 Questions

Schedule Variance (SV) is an essential component of Earned Value Management (EVM) that quantifies the difference between the work actually completed and the work planned to be completed at a given point in time. It is calculated by subtracting the Planned Value (PV) from the Earned Value (EV), expr…

Test mode:
PMI-SP - Schedule Variance (SV) Example Questions

Test your knowledge of Schedule Variance (SV)

Question 1

When calculating Schedule Variance (SV) in a project tracking system, how would a value of zero (SV = 0) be interpreted?

Question 2

When evaluating Schedule Variance (SV) in a project's earned value metrics, which calculation method best reflects the project's schedule performance status?

Question 3

Which of the following is true about Schedule Variance (SV) when calculating it using Earned Value Analysis?

More Schedule Variance (SV) questions
33 questions (total)