To-Complete Performance Index (TCPI)

5 minutes 5 Questions

The To-Complete Performance Index (TCPI) is a forecasting tool in Earned Value Management (EVM) that indicates the performance efficiency required to complete the remaining work within a specified budget. It is calculated by dividing the remaining work (measured in terms of budget) by the remaining…

Test mode:
PMI-SP - To-Complete Performance Index (TCPI) Example Questions

Test your knowledge of To-Complete Performance Index (TCPI)

Question 1

When should a project manager use the To-Complete Performance Index (TCPI)?

Question 2

A project is showing a TCPI value of 1.2. What does this indicate about the project's future cost performance requirements?

Question 3

A project manager needs to evaluate the performance required to achieve the project's cost objectives. Which formula should be used to calculate TCPI based on the budget at completion (BAC)?

More To-Complete Performance Index (TCPI) questions
24 questions (total)