PMI-SP - Estimating Activity Durations - Bottom-Up Estimating
Expert
1/46
In a project involving the renovation of multiple restaurants across different cities, the local teams have sent varied estimates for labor, materials, and fixtures. Which detail best amplifies the reliability of bottom-up estimating in this context?
a.
The sequential aggregation of estimates based on previous renovation projects and current market conditions in each city
b.
The systematic collection of detailed estimates that account for regional cost differences and supply chain considerations
c.
The comprehensive compilation of all resource estimates from different locations plus an additional percentage for regional economic factors
d.
The integration of local market variations and site-specific requirements into individual work package estimates
Expert