Three-Point Estimating

5 minutes 5 Questions

Three-point estimating is a technique used in project management to enhance the accuracy of activity duration estimates by considering uncertainty and risk. It involves estimating the most optimistic (O), most likely (M), and most pessimistic (P) durations for each activity and then calculating a w…

Test mode:
PMI-SP - Three-Point Estimating Example Questions

Test your knowledge of Three-Point Estimating

Question 1

You have a task in a new project with an optimistic time estimate of 2 hours, a most likely estimate of 4 hours, and a pessimistic estimate of 10 hours. What is the Beta Distribution estimate for this task?

Question 2

In your project, you're analyzing an essential task with the optimistic estimate of 15 days, the most likely estimate of 20 days, and the pessimistic estimate of 30 days. The client requests the calculation of time variance. What is your answer using Three-Point Estimating?

Question 3

A project manager is using Three-Point Estimating and wants to understand which factors most significantly affect the width of the estimation range (difference between pessimistic and optimistic estimates). Which statement is most accurate?

More Three-Point Estimating questions
54 questions (total)