PMI-SP - Identifying Stakeholders - Stakeholder Cube
Expert
1/9
When applying the Stakeholder Cube model in scheduling, what is the optimal timing for reassessing stakeholder positions?
a.
During quarterly executive meetings and project governance board reviews
b.
Only during the annual project performance review and stakeholder satisfaction surveys
c.
When stakeholders submit formal requests for schedule modifications and risk assessments
d.
At major project milestones and when significant schedule changes occur
Expert