PMI-SP - Managing Stakeholder Expectations - Schedule Risk Management
Expert
1/12
In schedule risk management, which tool best captures the interdependencies between risk events affecting multiple activities?
a.
Advanced correlation analysis with probability density functions and extended duration estimates
b.
Bayesian belief networks with schedule impact matrices
c.
Complex decision trees mapped to activity sequences and durations
d.
Risk breakdown structure integrated with schedule network diagrams