PMI-SP - Progress Measurement and Reporting - Schedule Baseline Management
Expert
1/12
Which element best describes the relationship between schedule baseline updates and configuration management?
a.
Schedule baselines are stored separately from configuration management to ensure data security
b.
Schedule baselines are updated whenever project stakeholders request modifications to maintain flexibility
c.
Schedule baselines follow version control procedures in configuration management
d.
Schedule baselines require unanimous stakeholder approval before each minor adjustment
Expert