Program Evaluation and Review Technique (PERT)

5 minutes 5 Questions

The Program Evaluation and Review Technique (PERT) is a statistical tool used in project management to analyze and represent the tasks involved in completing a project, particularly when the time required to complete different tasks is uncertain. Developed in the 1950s for the U.S. Navy's Polaris p…

Test mode:
PMI-SP - Program Evaluation and Review Technique (PERT) Example Questions

Test your knowledge of Program Evaluation and Review Technique (PERT)

Question 1

When using PERT analysis for scheduling, which statement best describes its primary advantage?

Question 2

In a PERT analysis, what does the formula (a + 4m + b)/6 calculate?

Question 3

In PERT analysis, which of these activities would require three time estimates (optimistic, most likely, and pessimistic)?

More Program Evaluation and Review Technique (PERT) questions
12 questions (total)