Schedule Compression Techniques

5 minutes 5 Questions

Schedule Compression Techniques are methods used in project management to shorten the project schedule without altering the project scope, to meet tight deadlines or compensate for delays. These techniques are critical when project timelines are constrained, and there is a need to accelerate project completion while maintaining quality and scope. The two primary Schedule Compression Techniques are Crashing and Fast Tracking. **Crashing** involves adding additional resources to critical path activities to complete them more rapidly. This may include assigning more personnel, increasing work hours through overtime, or utilizing higher-performance equipment. While crashing can reduce the project duration, it often results in increased costs due to the added resources. Therefore, project managers must perform cost-benefit analyses to determine if the time saved justifies the additional expense. **Fast Tracking** entails rescheduling tasks that were originally planned to occur sequentially to be performed in parallel or with some overlap. This approach can significantly reduce the project timeline but introduces additional risks. Overlapping tasks may lead to rework if dependent tasks are started before the preceding tasks are fully completed, potentially affecting project quality or causing further delays if issues arise. Implementing Schedule Compression Techniques requires careful analysis and planning. Project managers must assess the critical path to identify which activities impact the project completion date and evaluate the risks and costs associated with compressing those activities. They must also communicate effectively with stakeholders to manage expectations and obtain necessary approvals. It's important to note that while Schedule Compression can help meet project deadlines, it should not compromise the project's scope or quality. Project managers must ensure that accelerating the schedule does not lead to resource overutilization, decreased morale, or subpar deliverables. Proper risk management and continuous monitoring are essential to mitigate potential negative impacts. In essence, Schedule Compression Techniques are valuable tools for handling schedule constraints in project management. When applied judiciously, they enable project managers to deliver projects on time without sacrificing quality or scope, thereby enhancing the likelihood of project success.

Schedule Compression Techniques Guide

Why Schedule Compression Techniques are Important

Schedule compression techniques are critical in project management as they help teams meet project deadlines when the initial schedule shows completion later than required. These techniques are essential tools when:

• Projects face unexpected delays
• Stakeholders request earlier delivery dates
• Market conditions demand faster time-to-market
• Resource constraints change during project execution
• Regulatory or contractual deadlines must be met

Understanding these techniques is vital for PMI-SP certification and practical project management, as compressing schedules effectively can save projects from failure while managing impacts on cost, scope, and quality.

What are Schedule Compression Techniques?

Schedule compression techniques are methodologies used to shorten the project schedule duration while minimizing impact on project scope. The PMBOK Guide identifies two primary techniques:

1. Crashing: Adding resources to critical path activities to reduce duration, typically increasing costs.

2. Fast Tracking: Performing activities in parallel that would normally be done in sequence, increasing risk but not necessarily cost.

Additional techniques that may be covered include:

3. Scope Reduction: Removing or simplifying deliverables to meet deadlines.

4. Resource Optimization: Reallocating resources from non-critical to critical activities.

5. Calendar Adjustments: Adding shifts, extending work hours, or removing non-working periods.

How Schedule Compression Works

Crashing:
• Focuses on critical path activities that will impact the project end date
• Requires analyzing the cost-time tradeoff for each activity
• Implements the most cost-effective options first
• Example: Adding experienced developers to a coding task

Fast Tracking:
• Identifies activities that can overlap instead of being performed sequentially
• Increases communication requirements and coordination
• Elevates risk of rework if dependencies are violated
• Example: Starting software testing while final modules are still being developed

Implementation Process:

1. Identify the need for schedule compression
2. Analyze the current critical path
3. Evaluate compression options and their impacts
4. Select and implement optimal techniques
5. Monitor performance and adjust as needed

Comparing Crashing and Fast Tracking:

AspectCrashingFast Tracking
Cost ImpactTypically increases costsMay not increase direct costs
Risk LevelModerate riskHigher risk
Resource ImpactRequires additional resourcesRequires existing resources to work in parallel
When to UseWhen budget allows for additional resourcesWhen activities can safely overlap


Exam Tips: Answering Questions on Schedule Compression Techniques

1. Know the Key Differences
• Be able to clearly distinguish between crashing and fast tracking
• Understand that crashing adds resources and increases costs
• Remember that fast tracking increases risks but may not affect costs

2. Apply Critical Path Analysis
• Compression only works meaningfully when applied to critical path activities
• Recognize that compressing non-critical activities only increases float
• Identify when new critical paths emerge after compression

3. Calculate Compression Metrics
• Be prepared to calculate crash cost per time unit
• Know how to determine the optimal compression sequence
• Understand diminishing returns in schedule compression

4. Recognize Scenario Applications
• Practice identifying which technique is most appropriate for different scenarios
• Consider constraints on time, cost, resources, and risk tolerance
• Look for clues in the question that point to a specific technique

5. Remember the Limitations
• Acknowledge that there is always a practical limit to compression
• Understand the quality implications of aggressive compression
• Recognize when compression may be counterproductive

Common Exam Question Types:

• Scenario-based questions asking which technique to apply
• Calculation questions on crash costs and durations
• Questions on the impacts of each technique on project constraints
• Sequence questions on the proper implementation steps
• Analysis questions on how compression affects the network diagram

Sample Question and Analysis:

Question: A project manager needs to reduce the schedule by 2 weeks. Activity A can be crashed at $1,000 per day, saving 5 days. Activity B can be crashed at $1,500 per day, saving 10 days. Both are on the critical path. Which approach is most cost-effective?

Analysis:
• Activity A: $1,000 × 5 days = $5,000 for 5 days saved = $1,000 per day saved
• Activity B: $1,500 × 10 days = $15,000 for 10 days saved = $1,500 per day saved
• Most cost-effective: Crash Activity A first ($1,000 per day saved) then crash B as needed

By mastering these techniques and practicing with sample questions, you'll be well-prepared to handle schedule compression questions on your PMI-SP exam.

Test mode:
Go Premium

PMI Scheduling Professional Preparation Package (2025)

  • 3429 Superior-grade PMI Scheduling Professional practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PMI-SP preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Schedule Compression Techniques questions
33 questions (total)