PMI-SP - Reporting Schedule Status to Stakeholders - Earned Value Management (EVM) Metrics in Schedule Reporting
Expert
1/5
In a project using EVM metrics, what is the most accurate interpretation when the Schedule Performance Index (SPI) = 0.88, Cost Variance (CV) = -$15,000, and Schedule Variance (SV) = -$20,000 at the 50% completion point?