PMI-SP - Reporting Schedule Status to Stakeholders - Schedule Change Control and Reporting
Intermediate
1/12
During activity duration estimation for a major event management project, your team has access to three estimates for each activity: an optimistic estimate of 2 days, a most likely estimate of 4 days, and a pessimistic estimate of 12 days. Which value represents the expected duration using PERT?