PMI-SP - Reporting Schedule Status to Stakeholders - Communication of Schedule Risks and Mitigation Strategies
Expert
1/9
What is the recommended practice for presenting historical schedule risk data when proposing mitigation strategies to project sponsors?
a.
Present monthly schedule variance data through complex mathematical models and statistical distributions
b.
Use trend analysis with clear risk impact indicators and associated mitigation outcomes
c.
Create detailed technical reports listing all schedule risk events and their statistical probabilities of occurrence
d.
Compile extensive documentation of all past schedule delays with corresponding root cause analyses
Expert