PMI-SP - Resource Allocation and Leveling - Resource Calendars in Scheduling
Expert
1/12
During a multi-year project, when reviewing resource calendars for scheduling accuracy, what should be the primary focus?
a.
Documenting all overtime hours worked by team members in previous quarters
b.
Analyzing past resource performance metrics and attendance trends
c.
Recalculating historical resource utilization rates from previous calendar months
d.
Validating future resource availability patterns and time-off alignments
Expert