Fast Tracking
Fast Tracking is a schedule compression technique where activities or phases normally performed in sequence are undertaken in parallel for at least a portion of their duration. The objective is to reduce the project timeline without incurring additional costs typically associated with resource augmentation, as seen in crashing. In practice, fast tracking can involve starting a subsequent task before the predecessor task is fully completed. For example, beginning the design phase before the completion of requirements gathering. This approach can significantly shorten the project duration since tasks are overlapped rather than waiting for each to finish sequentially. However, fast tracking introduces additional risks and may increase the potential for rework. Overlapping tasks that are dependent on the outputs of previous activities can lead to errors if preceding tasks are not sufficiently complete to provide accurate input. This can result in quality issues, increased costs due to rework, and schedule delays if problems are discovered later in the project. Effective fast tracking requires careful analysis of the project schedule to identify tasks that can be overlapped with minimal risk. It often involves scrutinizing discretionary dependencies (soft logic), which are defined by the project team and can be adjusted as opposed to mandatory dependencies (hard logic), which are inherent to the work itself. Communication and coordination are critical when implementing fast tracking. Project managers must ensure that all team members understand the changes in the schedule and the expectations for their tasks. Regular monitoring and control are necessary to promptly identify and address any issues arising from the adjusted schedule. In essence, fast tracking is a strategy to expedite project completion by performing tasks in parallel, thereby reducing the overall schedule. While it can be effective in shortening project duration without additional costs, it requires meticulous planning and risk management to mitigate the potential negative impacts on quality and project objectives.
PMI-SP - Schedule Compression Techniques Example Questions
Test your knowledge of Amazon Simple Storage Service (S3)
Question 1
What is the primary risk associated with Fast Tracking in project scheduling?
Question 2
In a project where Fast Tracking is being implemented, what sequence of activities would be most appropriate to overlap?
Question 3
During fast tracking implementation, a project manager notices schedule compression efforts are not yielding expected results. What phase of fast tracking is most appropriate to evaluate next?
Go Premium
PMI Scheduling Professional Preparation Package (2024)
- 3429 Superior-grade PMI Scheduling Professional practice questions.
- Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
- Unlock Effortless PMI-SP preparation: 5 full exams.
- 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
- Bonus: If you upgrade now you get upgraded access to all courses
- Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!